Proses Perbaikan Saluran Penghubung Kelapa Cengkir Capai 40 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Kelapa Cengkir PHB Channel Repair Reaches 40 Percent

Repair on Kelapa Cengkir PHB channel's retaining walls in Kelapa Gading Timur Urban Village, Kelapa Gading, North Jakarta is now reached 40 percent.

Total, we repair 608 meters retaining wall.

Water Resources (SDA) Sub-dept.'s Kelapa Gading Sub-district Unit Head, Rukmana explained, retaining walls on both sides of the channel are repaired along 304 meters.

Halim Perdanakusuma Reservoir's Retaining Wall Repaired

"Total, we repair 608 meters retaining wall. Currently we have repaired 300 meters or about 40 percent," he informed, Monday (10/8).

He mentioned, previously the retaining walls were broken and tilted due to tree roots.

"Hopefully it can be finished in November," he stated.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1152 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye849 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye828 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye781 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye760 personAldi Geri Lumban Tobing